Pleasant Hill substation interconnection queue

1 active project totaling 72 MW in the SPP queue, plus 1 with terminal status (shown grayed).

1active projects
72active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2008-129 Not reported 161 72 Gas Operational
GEN-2011-026 Not reported 69 19.7 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.