Substation Scout

Philip Tap substation interconnection queue

1 active project totaling 300 MW in the SPP queue, plus 1 with terminal status (shown grayed).

2 SPP queue filings name Philip Tap as the point of interconnection, all in Haakon County, SD.

1active projects
300active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2017-014 Not reported 230 300 Wind Active
GEN-2017-019 Not reported 230 250 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.