North Fort Dodge Substation substation interconnection queue

1 active project totaling 100 MW in the SPP queue, plus 2 with terminal status (shown grayed).

3 SPP queue filings name North Fort Dodge Substation as the point of interconnection, all in Ford County, KS.

1active projects
100active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2020-SR4 Not reported 115 150 Wind Withdrawn
GEN-2019-044 Not reported 115 100 Solar Active
GEN-2024-105 Not reported 115 100 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.