Martin substation interconnection queue
1 active project totaling 159.1 MW in the SPP queue, plus 2 with terminal status (shown grayed).
1active projects
159.1active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2003-020 | Not reported | 115 | 159.1 | Wind | Operational |
| GEN-2017-113 | Not reported | 115 | 119 | Wind | Withdrawn |
| GEN-2016-161 | Not reported | 115 | 3 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.