Lawton East Side – Oklaunion line substation interconnection queue
0 active projects
totaling 0 MW in the SPP queue, plus 3 with terminal status (shown grayed).
3 SPP queue filings name Lawton East Side – Oklaunion line as the point of interconnection, all in Wilbarger County, TX.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2022-221
Not reported
345
350
Solar
Withdrawn
GEN-2022-222
Not reported
345
200
Battery
Withdrawn
GEN-2022-223
Not reported
345
200
Battery
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.