Hoskins Substation substation interconnection queue
2 active projects totaling 385 MW in the SPP queue, plus 3 with terminal status (shown grayed).
5 SPP queue filings name Hoskins Substation as the point of interconnection, all in Wayne County, NE.
2active projects
385active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2017-201 | Not reported | 345 | 250 | Wind | Active |
| GEN-2023-SR7 | Not reported | 345 | 135 | Battery | Active |
| GEN-2022-SR2 | Not reported | 345 | 100.8 | Battery | Withdrawn |
| GEN-2022-SR3 | Not reported | 345 | 100.2 | Solar | Withdrawn |
| GEN-2023-SR6 | Not reported | 345 | 100.2 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.