1 active project totaling 200 MW in the SPP queue, plus 2 with terminal status (shown grayed).

1active projects
200active MW
3total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-127 Not reported 345 1,300 Gas Withdrawn
GEN-2023-SR8 Not reported 345 200 Battery Active
GEN-2016-041 Not reported 345 100 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.