Substation Scout

Greenwood sub substation interconnection queue

2 active projects totaling 176.9 MW in the SPP queue.

2 SPP queue filings name Greenwood sub as the point of interconnection, all in Payne County, OK.

2active projects
176.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2017-071 Not reported 138 124.7 Solar Active
GEN-2017-072 Not reported 138 52.2 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first