0 active projects
totaling 0 MW in the SPP queue, plus 3 with terminal status (shown grayed).
3 SPP queue filings name Gracemont Substation as the point of interconnection, all in Caddo County, OK.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2023-164
Not reported
345
210
Battery
Withdrawn
GEN-2023-165
Not reported
345
210
Battery
Withdrawn
GEN-2023-150
Not reported
138
150
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.
Site Scanner
Before you spend weeks on a site, spend seconds screening it.