3 active projects totaling 506.7 MW in the SPP queue, plus 1 with terminal status (shown grayed).

4 SPP queue filings name Gordon Evans Substation as the point of interconnection, all in KS.

3active projects
506.7active MW
4total filed
Queue IDProjectkVMWResourceStatus
GEN-2017-179 Not reported 138 222 Wind Withdrawn
GEN-2017-226 Not reported 138 201.6 Solar Active
GEN-2017-227 Not reported 138 201.6 Battery Active
GEN-2017-068 Not reported 138 103.5 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.