0 active projects
totaling 0 MW in the SPP queue, plus 2 with terminal status (shown grayed).
2 SPP queue filings name Erick Substation as the point of interconnection, all in Beckham County, OK.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2015-055
Not reported
138
40
Solar
Withdrawn
GEN-2020-SR1
Not reported
138
40
Battery
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.
Site Scanner
Before you spend weeks on a site, spend seconds screening it.