Eddy County-Tolk (Crossroads) substation interconnection queue

4 active projects totaling 821.7 MW in the SPP queue, plus 2 with terminal status (shown grayed).

6 SPP queue filings name Eddy County-Tolk (Crossroads) as the point of interconnection, all in NM.

4active projects
821.7active MW
6total filed
Queue IDProjectkVMWResourceStatus
GEN-2008-022 Not reported 345 299.7 Wind Operational
GEN-2016-123 Not reported 345 298 Wind Operational
GEN-2017-078 Not reported 345 220 Wind Withdrawn
GEN-2016-124 Not reported 345 150 Wind Operational
GEN-2015-056 Not reported 345 101.2 Other Withdrawn
GEN-2016-125 Not reported 345 74 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.