Crossroads - Hobbs Line substation interconnection queue
0 active projects
totaling 0 MW in the SPP queue, plus 4 with terminal status (shown grayed).
4 SPP queue filings name Crossroads - Hobbs Line as the point of interconnection, all in NM.
0active projects
0active MW
4total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2023-081
Not reported
345
625
Hybrid
Withdrawn
GEN-2023-201
Not reported
345
300
Hybrid
Withdrawn
GEN-2022-159
Not reported
345
280
Wind
Withdrawn
GEN-2022-160
Not reported
345
280
Wind
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.