Clark County substation interconnection queue

2 active projects totaling 780 MW in the SPP queue, plus 2 with terminal status (shown grayed).

4 SPP queue filings name Clark County as the point of interconnection, all in KS.

2active projects
780active MW
4total filed
Queue IDProjectkVMWResourceStatus
GEN-2011-008 Not reported 345 600 Wind Operational
GEN-2011-023 Not reported 345 299 Wind Withdrawn
GEN-2012-012 Not reported 345 200 Wind Withdrawn
GEN-2012-024 Not reported 345 180 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.