Chappelle Creek substation interconnection queue

1 active project totaling 250.2 MW in the SPP queue, plus 6 with terminal status (shown grayed).

7 SPP queue filings name Chappelle Creek as the point of interconnection, all in Hyde County, SD.

1active projects
250.2active MW
7total filed
Queue IDProjectkVMWResourceStatus
GEN-2016-017 Not reported 345 250.2 Wind Operational
GEN-2022-068 Not reported 345 250 Wind Withdrawn
GEN-2022-069 Not reported 345 250 Wind Withdrawn
GEN-2022-070 Not reported 345 250 Wind Withdrawn
GEN-2023-105 Not reported 345 249 Wind Withdrawn
GEN-2016-103 Not reported 345 240 Wind Withdrawn
GEN-2016-092 Not reported 345 175 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.