Substation Scout

Carpenter Substation substation interconnection queue

1 active project totaling 150 MW in the SPP queue, plus 8 with terminal status (shown grayed).

9 SPP queue filings name Carpenter Substation as the point of interconnection, all in KS.

1active projects
150active MW
9total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-059 Not reported 345 500 Wind Withdrawn
GEN-2022-076 Not reported 345 500 Solar Withdrawn
GEN-2023-039 Not reported 345 250 Wind Withdrawn
GEN-2023-068 Not reported 345 250 Wind Withdrawn
GEN-2023-093 Not reported 345 250 Wind Withdrawn
GEN-2023-094 Not reported 345 250 Wind Withdrawn
GEN-2024-096 Not reported 345 200 Solar Withdrawn
GEN-2022-215 Not reported 345 154 Solar Withdrawn
GEN-2021-021 Not reported 345 150 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first