0 active projects
totaling 0 MW in the SPP queue, plus 2 with terminal status (shown grayed).
2 SPP queue filings name Atoka as the point of interconnection, all in Eddy County, NM.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2015-058
Not reported
115
50
Solar
Withdrawn
GEN-2010-021
Not reported
69
20
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.