0 active projects
totaling 0 MW in the SPP queue, plus 2 with terminal status (shown grayed).
2 SPP queue filings name Antelope - Hoskins Substation as the point of interconnection, all in Madison County, NE.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2018-068
Not reported
345
302.4
Wind
Withdrawn
GEN-2018-065
Not reported
345
19.8
Wind
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.