Substation Scout

SPP request GEN-2025-GR6

SPP queue ID GEN-2025-GR6

Queue request GEN-2025-GR6 was listed in the SPP interconnection queue at the end of 2025 as a 300 MW wind project in Dimmit County, TX, according to Berkeley Lab’s queue data file. The filing names Castro County as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue IDGEN-2025-GR6
Project nameNot reported
Status (as published)Active
SubstationCastro County
Point of interconnectionCastro County 115kV
CountyDimmit
StateTX
Voltage115 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Dimmit, TX: 1 request in the SPP queue, 1 active totaling 300 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySPS
ClusterReplacement; 05 SOUTHWEST
Interconnection serviceERIS
Project typeReplacement
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)None
Queue date2025-11-07

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.