SPP request GEN-2024-361

SPP queue ID GEN-2024-361

Queue request GEN-2024-361 was listed in the SPP interconnection queue at the end of 2025 as a 80 MW hybrid project in Lincoln County, OK, according to Berkeley Lab’s queue data file. The filing names Spring Valley - Warwick line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2029.

Queue IDGEN-2024-361
Project nameNot reported
Status (as published)Active
SubstationSpring Valley - Warwick line
Point of interconnectionSpring Valley - Warwick 138 kV line
CountyLincoln
StateOK
Voltage138 kV
Capacity80 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2029-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lincoln, OK: 6 requests in the SPP queue, 6 active totaling 815 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOGE
ClusterDISIS-2024-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)System Impact Study
Study phase (as the queue printed it)DISIS STAGE
Queue date2025-03-01
Components (hybrid)Solar 80 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.