SPP request GEN-2024-055
SPP queue ID GEN-2024-055
Queue request GEN-2024-055 was listed in the SPP interconnection queue at the end of 2025 as a 175 MW solar project in Vernon County, MO, according to Berkeley Lab’s queue data file. The filing names Butler - Nevada line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2029.
| Queue ID | GEN-2024-055 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Butler - Nevada line |
| Point of interconnection | Butler - Nevada 161 kV line |
| County | Vernon |
| State | MO |
| Voltage | 161 kV |
| Capacity | 175 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2029-12-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Vernon, MO: 2 requests in the SPP queue, 1 active totaling 175 MW.
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | WERE |
|---|---|
| Cluster | DISIS-2024-001; 03 CENTRAL |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | System Impact Study |
| Study phase (as the queue printed it) | DISIS STAGE |
| Queue date | 2024-10-30 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.