Substation Scout

SPP request GEN-2023-170

SPP queue ID GEN-2023-170

Queue request GEN-2023-170 was listed in the SPP interconnection queue at the end of 2025 as a 150 MW battery project in Chariton County, MO, according to Berkeley Lab’s queue data file. The filing names Salisbury Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2028.

Queue IDGEN-2023-170
Project nameNot reported
Status (as published)Active
SubstationSalisbury Substation
Point of interconnectionSalisbury 161 kV Substation
CountyChariton
StateMO
Voltage161 kV
Capacity150 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Chariton, MO: 1 request in the SPP queue, 1 active totaling 150 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWERE
ClusterDISIS-2023-001; 03 CENTRAL
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Facility Study
Study phase (as the queue printed it)FACILITY STUDY STAGE
Queue date2023-10-02

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.