SPP request GEN-2016-087

SPP queue ID GEN-2016-087

Queue request GEN-2016-087 was listed in the SPP interconnection queue at the end of 2025 as a 98.9 MW wind project in Campbell County, SD, according to Berkeley Lab’s queue data file. The filing names Campbell County line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2026.

Queue IDGEN-2016-087
Project nameNot reported
Status (as published)Active
SubstationCampbell County line
Point of interconnectionCampbell County 230 kV line
CountyCampbell
StateSD
Voltage230 kV
Capacity98.9 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2026-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Campbell, SD: 1 request in the SPP queue, 1 active totaling 98.9 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityWAPA
ClusterDISIS-2016-002-1; 01 NORTH
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/ON SCHEDULE
Queue date2016-07-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first