Queue request GEN-2001-039M was listed in the SPP interconnection queue at the end of 2025 as a 100 MW wind project in Wichita County, KS, according to Berkeley Lab’s queue data file. The filing names Central Plains Tap as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 1, 2008.

Queue IDGEN-2001-039M
Project nameNot reported
Status (as published)Operational
SubstationCentral Plains Tap
Point of interconnectionCentral Plains Tap 115kV
CountyWichita
StateKS
Voltage115 kV
Capacity100 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2008-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wichita, KS: 2 requests in the SPP queue, 1 active totaling 100 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySUNC
ClusterICS-2008-001 Prior Queued; 03 CENTRAL
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2001-11-01
Operational date2008-12-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first