Substation Scout

SPP request ERAS-2025-009

SPP queue ID ERAS-2025-009

Queue request ERAS-2025-009 was listed in the SPP interconnection queue at the end of 2025 as a 450 MW coal project in Chouteau County, OK, according to Berkeley Lab’s queue data file. The filing names Grec #1 Interconnect Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2026.

Queue IDERAS-2025-009
Project nameNot reported
Status (as published)Active
SubstationGrec #1 Interconnect Substation
Point of interconnectionGrec #1 Interconnect 161kV Substation
CountyChouteau
StateOK
Voltage161 kV
Capacity450 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Proposed online date2026-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Chouteau, OK: 5 requests in the SPP queue, 3 active totaling 1,144 MW.

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityGRDA
ClusterERAS-2025-001; 04 SOUTHEAST
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)ERAS
Queue date2025-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first