SPP request ASGI-2017-006
SPP queue ID ASGI-2017-006
Queue request ASGI-2017-006 was listed in the SPP interconnection queue at the end of 2025 as a 238 MW wind project, according to Berkeley Lab’s queue data file. The filing names Maryville as its point of interconnection. Its status as of December 31, 2025 was “Operational”.
| Queue ID | ASGI-2017-006 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Maryville |
| Point of interconnection | Maryville 161kV |
| County | Not reported |
| State | Not reported |
| Voltage | 161 kV |
| Capacity | 238 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Maryville substation: 2 requests in the SPP queue, 2 active totaling 468 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| ASGI-2018-001 | Not reported | 230 | Wind | Operational |
Tracked changes
Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Study phase (standardized by Berkeley Lab) | IA Executed |
|---|---|
| Study phase (as the queue printed it) | IA FULLY EXECUTED/COMMERCIAL OPERATION |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.