Substation Scout

SPP request ASGI-2016-003

SPP queue ID ASGI-2016-003

Queue request ASGI-2016-003 was listed in the SPP interconnection queue at the end of 2025 as a 12 MW gas project, according to Berkeley Lab’s queue data file. The filing names Paola as its point of interconnection. Its status as of December 31, 2025 was “Operational”.

Queue IDASGI-2016-003
Project nameNot reported
Status (as published)Operational
SubstationPaola
Point of interconnectionPaola 161kV
CountyNot reported
StateNot reported
Voltage161 kV
Capacity12 MW
Resource (as published)Gas
Resource categoryGas (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Tracked changes

Not tracked. SPP rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue date2016-08-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first