Yell, AR interconnection queue
1 active project totaling 150 MW in the SPP queue, plus 1 with terminal status (shown grayed).
1active projects
150active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| ERAS-2025-005 | Not reported | 161 | 150 | Hybrid | Active |
| GEN-2024-335 | Not reported | 161 | 150 | Hybrid | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.