Woods, OK interconnection queue

5 active projects totaling 1,230 MW in the SPP queue, plus 3 with terminal status (shown grayed).

5active projects
1,230active MW
8total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-102 Not reported 345 475 Hybrid Active
GEN-2023-100 Not reported 345 300 Hybrid Withdrawn
GEN-2024-134 Not reported 345 250 Wind Active
GEN-2024-135 Not reported 345 250 Wind Active
GEN-2015-095 Not reported 138 176 Wind Withdrawn
GEN-2019-045 Not reported 138 155 Solar Active
GEN-2023-104 Not reported 138 100 Hybrid Active
GEN-2019-046 Not reported 138 90 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.