Substation Scout

Washington, KS interconnection queue

1 active project totaling 302 MW in the SPP queue, plus 1 with terminal status (shown grayed).

1active projects
302active MW
2total filed
Queue IDProjectkVMWResourceStatus
GEN-2016-149 Not reported 345 302 Wind Operational
GEN-2022-081 Not reported 115 218 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first