Substation Scout

Texas, OK interconnection queue

12 active projects totaling 2,352.6 MW in the SPP queue, plus 18 with terminal status (shown grayed).

12active projects
2,352.6active MW
30total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-127 Not reported 345 1,300 Gas Withdrawn
GEN-2007-041 Not reported n/r 600 Wind Withdrawn
GEN-2008-028 Not reported n/r 360 Wind Withdrawn
GEN-2016-141 Not reported 345 350 Wind Active
GEN-2016-142 Not reported 345 350 Wind Active
GEN-2008-110 Not reported n/r 299.2 Wind Withdrawn
GEN-2007-046 Not reported 115 200 Wind Operational
GEN-2014-037 Not reported 345 200 Wind Withdrawn
GEN-2022-157 Not reported 345 200 Solar Withdrawn
GEN-2016-133 Not reported 345 187.5 Wind Active
GEN-2016-134 Not reported 345 187.5 Wind Active
GEN-2016-137 Not reported 345 187.5 Wind Active
GEN-2016-138 Not reported 345 187.5 Wind Active
GEN-2016-143 Not reported 345 175 Wind Withdrawn
GEN-2016-144 Not reported 345 175 Wind Withdrawn
GEN-2016-145 Not reported 345 175 Wind Active
GEN-2016-146 Not reported 345 175 Wind Active
GEN-2002-006 Not reported n/r 150 Wind Withdrawn
GEN-2008-109 Not reported n/r 150 Wind Withdrawn
GEN-2024-244 Not reported 115 150 Battery Active
GEN-2017-100 Not reported 115 102.6 Solar Active
GEN-2017-089 Not reported 115 102 Solar Withdrawn
GEN-2016-041 Not reported 345 100 Solar Withdrawn
GEN-2016-135 Not reported 345 100 Wind Withdrawn
GEN-2016-139 Not reported 345 100 Wind Active
GEN-2016-156 Not reported n/r 100 Solar Withdrawn
GEN-2016-136 Not reported 345 75 Wind Withdrawn
GEN-2016-140 Not reported 345 75 Wind Withdrawn
GEN-2017-162 Not reported 115 50 Wind Withdrawn
GEN-2009-073T Not reported 69 46.5 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first