| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2020-068 | Not reported | 345 | 400 | Solar | Withdrawn |
| GEN-2020-067 | Not reported | 345 | 352.5 | Wind | Active |
| GEN-2006-030 | Not reported | n/r | 150 | Wind | Withdrawn |
| GEN-2007-004 | Not reported | n/r | 150 | Wind | Withdrawn |
| GEN-2017-187 | Not reported | 115 | 150 | Solar | Active |
| GEN-2021-054 | Not reported | 115 | 150 | Solar | Withdrawn |
| GEN-2016-090 | Not reported | 115 | 100 | Solar | Withdrawn |
| GEN-2016-077 | Not reported | 69 | 54 | Solar | Withdrawn |
| GEN-2014-044 | Not reported | 115 | 50 | Solar | Withdrawn |
| GEN-2018-086 | Not reported | 115 | 50 | Battery | Withdrawn |