Substation Scout

Stanton, KS interconnection queue

1 active project totaling 20 MW in the SPP queue, plus 4 with terminal status (shown grayed).

1active projects
20active MW
5total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-039 Not reported 345 250 Wind Withdrawn
GEN-2023-068 Not reported 345 250 Wind Withdrawn
GEN-2017-052 Not reported 115 25 Solar Withdrawn
GEN-2014-071 Not reported 115 20 Solar Withdrawn
GEN-2015-021 Not reported 115 20 Solar Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.