Seward, KS interconnection queue
2 active projects totaling 349 MW in the SPP queue, plus 7 with terminal status (shown grayed).
2active projects
349active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2010-027 | Not reported | 345 | 900 | Wind | Withdrawn |
| GEN-2008-133 | Not reported | n/r | 800 | Wind | Withdrawn |
| GEN-2006-049 | Not reported | 345 | 400 | Wind | Withdrawn |
| GEN-2024-218 | Not reported | 115 | 199 | Hybrid | Active |
| GEN-2018-009 | Not reported | 115 | 150 | Wind | Active |
| GEN-2021-087 | Not reported | 115 | 100 | Hybrid | Withdrawn |
| GEN-2008-080 | Not reported | n/r | 80 | Wind | Withdrawn |
| GEN-2019-059 | Not reported | 115 | 75 | Solar | Withdrawn |
| GEN-2020-082 | Not reported | 115 | 20 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.
Site Scanner