Sargent, ND interconnection queue
1 active project totaling 175 MW in the SPP queue.
1active projects
175active MW
1total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2024-034 | Not reported | 115 | 175 | Battery | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.