Rogers, OK interconnection queue
3 active projects totaling 745 MW in the SPP queue, plus 6 with terminal status (shown grayed).
3active projects
745active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2006-004 | Not reported | n/r | 620 | Coal | Withdrawn |
| GEN-2006-005 | Not reported | n/r | 580 | Coal | Withdrawn |
| ERAS-2025-023 | Not reported | 345 | 510 | Gas | Active |
| GEN-2024-087 | Not reported | 345 | 510 | Gas | Withdrawn |
| GEN-2022-234 | Not reported | 138 | 200 | Solar | Withdrawn |
| GEN-2023-103 | Not reported | 138 | 200 | Battery | Withdrawn |
| GEN-2023-063 | Not reported | 138 | 135 | Hybrid | Active |
| GEN-2022-001 | Not reported | 138 | 100 | Battery | Withdrawn |
| GEN-2024-SR16 | Not reported | 138 | 100 | Battery | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.