Substation Scout

Randall, TX interconnection queue

2 active projects totaling 550 MW in the SPP queue, plus 17 with terminal status (shown grayed).

2active projects
550active MW
19total filed
Queue IDProjectkVMWResourceStatus
GEN-2006-039 Not reported 230 400 Wind Withdrawn
GEN-2007-048 Not reported 230 400 Wind Withdrawn
GEN-2013-031 Not reported 230 370 Gas Withdrawn
GEN-2017-081 Not reported 230 300 Solar Withdrawn
GEN-2023-086 Not reported 230 300 Hybrid Withdrawn
GEN-2024-364 Not reported 230 300 Hybrid Active
GEN-2024-153 Not reported 230 250 Solar Active
GEN-2006-045 Not reported 230 240 Wind Withdrawn
GEN-2006-047 Not reported 230 240 Wind Withdrawn
GEN-2008-120 Not reported n/r 239.2 Wind Withdrawn
GEN-2018-077 Not reported n/r 150 Solar Withdrawn
GEN-2022-008 Not reported 230 150 Solar Withdrawn
GEN-2022-150 Not reported 115 150 Battery Withdrawn
GEN-2023-185 Not reported 230 150 Solar Withdrawn
GEN-2023-209 Not reported 115 125 Battery Withdrawn
GEN-2015-022 Not reported 115 112 Solar Withdrawn
GEN-2016-039 Not reported 115 112 Solar Withdrawn
GEN-2019-056 Not reported 115 100 Battery Withdrawn
GEN-2017-106 Not reported 115 40 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first