Osage, KS interconnection queue
2 active projects totaling 500 MW in the SPP queue, plus 7 with terminal status (shown grayed).
2active projects
500active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2017-125 | Not reported | 345 | 252 | Wind | Withdrawn |
| GEN-2017-127 | Not reported | 345 | 252 | Wind | Withdrawn |
| GEN-2020-071 | Not reported | 230 | 252 | Wind | Withdrawn |
| GEN-2023-220 | Not reported | 345 | 250 | Solar | Active |
| GEN-2023-221 | Not reported | 345 | 250 | Solar | Active |
| GEN-2017-130 | Not reported | 345 | 215 | Wind | Withdrawn |
| GEN-2017-191 | Not reported | 345 | 201.6 | Solar | Withdrawn |
| GEN-2023-219 | Not reported | 115 | 125 | Solar | Withdrawn |
| GEN-2017-192 | Not reported | 345 | 52 | Battery | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.