Nodaway, MO interconnection queue
2 active projects totaling 901.2 MW in the SPP queue, plus 7 with terminal status (shown grayed).
2active projects
901.2active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| ERAS-2025-007 | Not reported | 345 | 450.6 | Gas | Active |
| ERAS-2025-013 | Not reported | 345 | 450.6 | Gas | Active |
| GEN-2024-028 | Not reported | 345 | 450.6 | Gas | Withdrawn |
| GEN-2024-053 | Not reported | 345 | 450.6 | Gas | Withdrawn |
| GEN-2006-017 | Not reported | 161 | 300 | Wind | Withdrawn |
| GEN-2018-022 | Not reported | 345 | 300 | Solar | Withdrawn |
| GEN-2007-053 | Not reported | 161 | 110 | Wind | Withdrawn |
| GEN-2007-016 | Not reported | n/r | 100.5 | Wind | Withdrawn |
| GEN-2007-017 | Not reported | 161 | 100.5 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.