Nodaway, MO interconnection queue

2 active projects totaling 901.2 MW in the SPP queue, plus 7 with terminal status (shown grayed).

2active projects
901.2active MW
9total filed
Queue IDProjectkVMWResourceStatus
ERAS-2025-007 Not reported 345 450.6 Gas Active
ERAS-2025-013 Not reported 345 450.6 Gas Active
GEN-2024-028 Not reported 345 450.6 Gas Withdrawn
GEN-2024-053 Not reported 345 450.6 Gas Withdrawn
GEN-2006-017 Not reported 161 300 Wind Withdrawn
GEN-2018-022 Not reported 345 300 Solar Withdrawn
GEN-2007-053 Not reported 161 110 Wind Withdrawn
GEN-2007-016 Not reported n/r 100.5 Wind Withdrawn
GEN-2007-017 Not reported 161 100.5 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.