Substation Scout

Mcintosh, OK interconnection queue

3 active projects totaling 501 MW in the SPP queue, plus 3 with terminal status (shown grayed).

3active projects
501active MW
6total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-022 Not reported 345 250 Wind Withdrawn
GEN-2022-074 Not reported 138 220.9 Wind Withdrawn
GEN-2023-041 Not reported 138 190 Solar Withdrawn
GEN-2024-296 Not reported 345 167 Solar Active
GEN-2024-297 Not reported 345 167 Solar Active
GEN-2024-298 Not reported 345 167 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.