Substation Scout

Madison, NE interconnection queue

1 active project totaling 170 MW in the SPP queue, plus 11 with terminal status (shown grayed).

1active projects
170active MW
12total filed
Queue IDProjectkVMWResourceStatus
GEN-2018-068 Not reported 345 302.4 Wind Withdrawn
GEN-2021-058 Not reported 345 300 Wind Withdrawn
GEN-2018-083 Not reported 345 250 Wind Withdrawn
GEN-2025-SR31 Not reported 345 170 Battery Active
GEN-2006-044N02 Not reported 230 100.5 Wind Withdrawn
GEN-2010-010 Not reported 230 100.5 Wind Withdrawn
GEN-2006-038N014 Not reported n/r 100 Wind Withdrawn
GEN-2019-069 Not reported 345 100 Solar Withdrawn
GEN-2019-073 Not reported 345 100 Solar Withdrawn
GEN-2013-006 Not reported 230 50.6 Wind Withdrawn
GEN-2019-070 Not reported 345 50 Solar Withdrawn
GEN-2018-065 Not reported 345 19.8 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first