Leavenworth, KS interconnection queue

3 active projects totaling 799 MW in the SPP queue, plus 5 with terminal status (shown grayed).

3active projects
799active MW
8total filed
Queue IDProjectkVMWResourceStatus
GEN-2001-009 Not reported n/r 640 Gas Withdrawn
GEN-2001-010 Not reported n/r 640 Gas Withdrawn
GEN-2024-253 Not reported 345 300 Hybrid Active
GEN-2024-339 Not reported 115 300 Battery Active
GEN-2018-058 Not reported 345 252 Solar Withdrawn
GEN-2018-059 Not reported 345 252 Solar Withdrawn
GEN-2024-121 Not reported 115 199 Battery Active
GEN-2017-123 Not reported 345 180 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.