Hyde, SD interconnection queue
2 active projects totaling 450.2 MW in the SPP queue, plus 10 with terminal status (shown grayed).
2active projects
450.2active MW
12total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2023-106 | Not reported | 345 | 504 | Wind | Withdrawn |
| GEN-2016-017 | Not reported | 345 | 250.2 | Wind | Operational |
| GEN-2022-068 | Not reported | 345 | 250 | Wind | Withdrawn |
| GEN-2022-069 | Not reported | 345 | 250 | Wind | Withdrawn |
| GEN-2022-070 | Not reported | 345 | 250 | Wind | Withdrawn |
| GEN-2024-202 | Not reported | 345 | 250 | Wind | Withdrawn |
| GEN-2023-105 | Not reported | 345 | 249 | Wind | Withdrawn |
| GEN-2016-103 | Not reported | 345 | 240 | Wind | Withdrawn |
| GEN-2022-169 | Not reported | 345 | 220 | Hybrid | Withdrawn |
| GEN-2018-129 | Not reported | 230 | 200.2 | Wind | Withdrawn |
| GEN-2016-094 | Not reported | 230 | 200 | Wind | Operational |
| GEN-2016-092 | Not reported | 345 | 175 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.