Hutchinson, TX interconnection queue

2 active projects totaling 600 MW in the SPP queue, plus 7 with terminal status (shown grayed).

2active projects
600active MW
9total filed
Queue IDProjectkVMWResourceStatus
GEN-2022-063 Not reported 115 350 Solar Withdrawn
GEN-2024-077 Not reported 230 300 Solar Active
GEN-2024-078 Not reported 230 300 Solar Active
GEN-2005-007 Not reported n/r 260 Gas Withdrawn
GEN-2007-005 Not reported n/r 200 Wind Withdrawn
GEN-2007-033 Not reported n/r 200 Wind Withdrawn
GEN-2003-016 Not reported n/r 100.5 Wind Withdrawn
GEN-2005-002 Not reported n/r 80 Wind Withdrawn
GEN-2010-007 Not reported 115 73.8 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.