0 active projects
totaling 0 MW in the SPP queue, plus 6 with terminal status (shown grayed).
0active projects
0active MW
6total filed
Queue ID
Project
kV
MW
Resource
Status
GEN-2009-012
Not reported
345
300
Wind
Withdrawn
GEN-2009-029
Not reported
161
300
Wind
Withdrawn
GEN-2010-056
Not reported
345
151.2
Wind
Withdrawn
GEN-2013-026
Not reported
345
150
Wind
Withdrawn
GEN-2009-031
Not reported
69
149.5
Wind
Withdrawn
GEN-2018-014
Not reported
345
74.1
Wind
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with SPP before relying on these figures.