Queue IDProjectkVMWResourceStatus
GEN-2021-070 Not reported 345 504 Wind Active
GEN-2017-183 Not reported 345 400 Wind Active
GEN-2017-184 Not reported 345 400 Solar Active
GEN-2011-017 Not reported 345 299 Wind Withdrawn
GEN-2021-068 Not reported 345 249.6 Wind Active
GEN-2021-069 Not reported 345 249.6 Wind Active
GEN-2010-015 Not reported 345 200.1 Wind Withdrawn
GEN-2011-016 Not reported 345 200.1 Wind Withdrawn
GEN-2010-054 Not reported 345 200 Wind Withdrawn
GEN-2017-049 Not reported 69 50 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first