Greeley, NE interconnection queue
2 active projects totaling 185 MW in the SPP queue, plus 2 with terminal status (shown grayed).
2active projects
185active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| GEN-2017-234 | Not reported | 115 | 115 | Wind | Active |
| GEN-2006-038N023 | Not reported | n/r | 100 | Wind | Withdrawn |
| GEN-2013-023 | Not reported | 115 | 74.8 | Wind | Withdrawn |
| GEN-2024-SR8 | Not reported | 115 | 70 | Battery | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.