3 active projects totaling 753.6 MW in the SPP queue, plus 6 with terminal status (shown grayed).

3active projects
753.6active MW
9total filed
Queue IDProjectkVMWResourceStatus
GEN-2008-091 Not reported n/r 300 Wind Withdrawn
GEN-2017-207 Not reported n/r 300 Solar Withdrawn
GEN-2017-213 Not reported 345 300 Solar Withdrawn
GEN-2025-GR1 Not reported 345 300 Wind Active
GEN-2013-029 Not reported 345 299 Wind Operational
GEN-2017-203 Not reported 345 210 Solar Withdrawn
GEN-2015-003 Not reported 345 200 Wind Withdrawn
GEN-2016-072 Not reported 345 156 Wind Withdrawn
GEN-2015-015 Not reported 138 154.6 Wind Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.