Substation Scout

Garvin, OK interconnection queue

1 active project totaling 200 MW in the SPP queue, plus 3 with terminal status (shown grayed).

1active projects
200active MW
4total filed
Queue IDProjectkVMWResourceStatus
GEN-2023-177 Not reported 138 200 Solar Active
GEN-2024-163 Not reported 138 199 Battery Withdrawn
GEN-2022-166 Not reported 138 150 Solar Withdrawn
GEN-2023-174 Not reported 138 150 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.