2 active projects totaling 258 MW in the SPP queue, plus 7 with terminal status (shown grayed).

2active projects
258active MW
9total filed
Queue IDProjectkVMWResourceStatus
GEN-2004-010 Not reported n/r 300 Wind Withdrawn
GEN-2011-002 Not reported 69 300 Wind Withdrawn
GEN-2011-039 Not reported 345 300 Wind Withdrawn
GEN-2024-061 Not reported 138 200 Battery Active
GEN-2011-004 Not reported 138 150.4 Wind Withdrawn
GEN-2022-041 Not reported 69 100 Solar Withdrawn
GEN-2020-003 Not reported 69 58 Hybrid Active
GEN-2023-121 Not reported 69 50 Solar Withdrawn
GEN-2016-173 Not reported 69 42 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.